charter oak acc102 week 11 test part 1

$17.00

Description

·

Controlling the materials price variance is
usually the responsibility of:

Answer

·
Question 2

3.75 out of 3.75 points

2. Controlling the
materials quantity variance is usually the responsibility of:

Answer

·
Question 3

3.75 out of 3.75 points

3. The use of
inexpensive, low quality, materials often results in:

Answer

·
Question 4

3.75 out of 3.75 points

4. Excessive
overtime hours worked by direct labor workers often results in:

Answer

·
Question 5

3.75 out of 3.75 points

5. An unfavorable
overhead volume variance results from:

Answer

·
Question 6

0 out of 3.75 points

6. If fewer units are produced than had been
estimated when standard unit costs were determined, there would normally be:

Answer

·
Question 7

3.75 out of 3.75 points

7. Overhead volume variances indicate:

Answer

·
Question 8

3.75 out of 3.75 points

8. Which statement is true regarding a standard
cost system?

Answer

·
Question 9

3.75 out of 3.75 points

9. The overhead spending variance:

Answer

·
Question 10

3.75 out of 3.75 points

Use the following to answer questions 10-12:

Tony’s Inc. flexible budget for June, based upon
actual output, called for the use of 10,000 pounds of materials at a standard
cost of $6.10 per pound. The Production Department actually used 10,300
pounds of materials costing $5.80 per pound during June.

10. Refer to the information above. Tony’s
materials price variance for June is:

Answer

·
Question 11

3.75 out of 3.75 points

11. Refer to the information above. The materials
quantity variance for Tony’s June operations is:

Answer

·
Question 12

3.75 out of 3.75 points

12. Refer to the information above. The journal
entry to record the cost of direct materials used in June includes each of
the following except:

Answer

·
Question 13

3.75 out of 3.75 points

Use the following to answer questions 13-16:

Seaside Company’s flexible budget, based upon the
number of equivalent units produced, called for the use of 5,000 square yards
of fabric at a standard cost of $2.10 per square yard. The Production
Department actually used 5,200 square yards costing $1.95 per square yard
during June.

13. Refer to the information above. The materials
price variance for Seaside Company for June is:

Answer

·
Question 14

3.75 out of 3.75 points

14. Refer to the information above. The materials
quantity variance for Seaside Company for June is:

Answer

·
Question 15

3.75 out of 3.75 points

15. Refer to the information above. The journal entry
to record the cost of direct materials used in March includes:

Answer

·
Question 16

3.75 out of 3.75 points

16. Refer to the information above. With respect
to materials costs, the supervisor of the Production Department should be
held responsible for:

Answer

·
Question 17

3.75 out of 3.75 points

Use the following to answer questions 17-20:

Vista Mfg.’s July production involved actual
direct labor costs of $46,287 for 3,700 direct labor hours. The budget for
the July level of production called for 3,800 direct labor hours at $12.50
per hour, using a standard cost system.

17. Refer to the information above. With respect
to labor costs, Vista/>’s production manager is responsible for:

Answer

·
Question 18

3.75 out of 3.75 points

18. Refer to the information above. Vista/>’s
labor rate variance for July is:

Answer

·
Question 19

3.75 out of 3.75 points

19. Refer to the information above. Vista/>’s
labor efficiency variance for July is:

Answer

·
Question 20

3.75 out of 3.75 points

20. Refer to the information above. Which of the
following is the most likely explanation for the types of labor variances
resulting from Vista/>’s July operations?

Answer

\

Reviews

There are no reviews yet.

Be the first to review “charter oak acc102 week 11 test part 1”

Your email address will not be published. Required fields are marked *